Red Bull Arena Update
Apparently the construction of Red Bull Arena will be a transparent process, as Our Sports Central
reports that NYRB will be providing fans with regular updates about progress at Harrison, NJ.
Here is an excerpt:
In the first week of above ground construction of Red Bull Arena, 872 pieces of steel (a total
of 206 tons) have been set in place.
The D.C. United Stadium Report @ Aug 26, 2008 07:22 PM EST | Blog Profile
Tags: sports, red bull, Red Bull Arena

Save This Page
